Krause Logo Instructions for assembly and use 

Assembly Scaffold

KRAUSE 916105 CORDA Assembly ScaffoldKRAUSE 916105 CORDA Assembly Scaffold - ICON 1

A Art.-No. 916105
Art.-No. 950009
B Art.-No. 916112
Art.-No. 950016
A+B Art.-No. 916129
Art.-No. 950023

KRAUSE 916105 CORDA Assembly Scaffold - FIGURE 1

Assembly Package A 

KRAUSE 916105 CORDA Assembly Scaffold - Assembly Package

Assembly Package A+B 

KRAUSE 916105 CORDA Assembly Scaffold - Assembly Package 2KRAUSE 916105 CORDA Assembly Scaffold - Assembly Package 3KRAUSE 916105 CORDA Assembly Scaffold - Assembly Package 4

Anchorage of the scaffold at a wall
Starting with package A, the scaffold must be fastened to the wall using one stabilizing set when in use as wall scaffold. When using package A+B with two wall clearance anchors.
While using the stabilizing sets it is important to ensure that they are always installed below the top platform.
To fix the stabilizing sets in the wall, 12 mm diameter eyebolts must be used. Selection of appropriate dowels depends on the wall structure.

KRAUSE 916105 CORDA Assembly Scaffold - Assembly Package 5

Maintenance and servicing

  • Prior to assembly of the scaffold all parts must be checked for possible damage and damaged parts must be replaced. Original spare parts may be used only.
  • All welding seams and other materials must undergo a visual magnaflux inspection. Further, the scaffold com ponents must not be deformed or crushed. Flawless functionality of construction components such as jaws, mandrels, wheels etc. must be ensured.
  • The parts must be thrown to avoid damage.
  • The scaffold components must be stored in such a way that they cannot be damaged.
  • The individual parts must be stored laying and sheltered from the weather.
  • During the transport, the construction components must be secured against damage inflicted by slipping, bumping, falling etc.
  • For cleaning of scaffold components use water and customary cleansing agents. Colour stains can be removed by using turpentine.
  • The assembly scaffold must be anchored and secured against unauthorized use after the end of work.
  • Extras, accessories, assembly aids etc. are not included in the scope of delivery.
  • No liability for improper use.

560823 © 2023 by ILN40091990 00 00 2. Printed in Germany.
We reserve the right to make technical changes and do not accept any liability for printing errors and mistakes.

Hersteller/Manufacturer:
KRAUSE-Werk GmbH & Co. KG
Am Kreuzweg 3
D-36304 Alsfeld
Tel.: +49 (0) 6631 795-0
Fax: +49 (0) 6631 795-139
www.krause-systems.com

Leave a Comment